168 Hours Trial Operation Completions of MAMUJU Unit 2#- Shandong Lineng Electric Technology Co., Ltd.

Viewed:Date:2019-01-08 15:26
168 Hours Trial Operation Completions of MAMUJU Unit 2#
 
  At 11:16 on August 9, 2018, Indonesia's MAMUJU project unit 2# completed 168 hours Trial Operation, which is another major node after 168 hours Trial Operation  of unit 1# during commissioning period.
 
  Compared with Unit 1#, the 168-hour Trial Operation process of Unit 2# is full of greater challenges. Because the ash content of coal used in site commissioning is up to 18%, it brings a great test for the operation of boiler and electrostatic precipitation, ash removal and slag removal, and also a test for the adjustment level and responsibility consciousness of operators.
 
  All the staff of MAMUJU Project Department of Lineng Electric Company dare to challenge and work hard together to ensure the successful completion of the unit trial operation with professional skills and rigorous working attitude. The whole trial operation has been highly praised by the owner, the general contractor and the third supervisor of Indonesia.
 