      On December 28, 2017, 12:43,initial turning of 1# unit of Indonesia MAMUJU 2*25MW coal-fired power station is successful with the constant speed is 3000 RPM, And the completion of this node marks the 1 # unit basically enjoys the requirement for whole startup and synchronization.
      Our company is responsible for the overall operation and maintenance of the TOC stage of this project, the training for the owner staff, and the 5-year overall business operation and maintenance. Since entering on-site in July 2017, our staff earnestly shoulder the field debugging operations, equipment management, on-site safety management, production material preparation, the task of personnel training, staff of all the project department make concerted effort, overcome various external difficulties and internal conditions as well as go hand in hand to get through difficulties under the limited condition, and we timely complete the plant commissioning and turn the unit successfully for the first time, which make us get the highly recognized of the owner and the EPC party. 
      1 # unit commissioning has been completed, 2 # unit work is just beginning, and the LNET staff with high ambition will continue to carry forward the fighting spirit and bear hardships and stand hard work spirit as well as strive to obtain new heights for the company by our persistent, boldness and diligence! 