The reverse energization of 110kV booster station of the tec- Shandong Lineng Electric Technology Co., Ltd.

Viewed:Date:2020-04-21 08:09

The reverse energization of 110kV booster station of the technical modification project of Huzhou Zhili changhe thermoelectric 15MW high temperature and high pressure unit is completed successfully
 

      On April 15, 2020, the reverse energization of 110kV booster station of the technical modification project of Huzhou Zhili changhe thermoelectric 15MW high temperature and high pressure unit,which is debugged by LNET,  is completed successfully.

      For the sake of making sure the smoothness of the reverse energization of the booster station, the trial-run headquarters attaches great importance to it with strengthening the coordination between the internal and external organizations, making full preparations for the startup of site equipment by  cooperating with the owner, supervision, design unit and construction units. The leaders convene a coordination meeting, and make detailed deployment of off-site and on-site system operation, on-site safety measures and other works; According to the "Debugging Program of 110kV Booster Station Reverse Energization ", the corresponding safety measures and emergency plan are formulated.

      Before the reverse energization, the station switch transmission test, subsystem debugging of monomer equipment, interlocking commissioning of the whole system etc., are conducted and the safety and integrity of the system and equipment involved in the reverse energization has been checked in succession, so as to eliminate the potential risks in all aspects. In the process of reverse energization, the operation is strictly performed in accordance with the "Debugging Program of 110kV Booster Station Reverse Energization", and the commissioning director conducts on-site command and coordination throughout the whole process to ensure the smoothness  of reverse energization, which is highly recognized by the owner and the supervisor.

      The reverse energization of 110KV booster station is an paramount link before the whole project is started, which provides a strong guarantee for the later subsystem debugging of  all majors.